ORENDA OSCII PROJECTS – BATTERY ENERGY STORAGE SYSTEM
Site
Bronx and Staten Island, New York
Project
ORENDA OSCII PROJECTS – BATTERY ENERGY STORAGE SYSTEM
Role
EPC Contractor
- DCO. In JV with Jingoli Power, providing major equipment procurement and construction on BESS projects.
- Includes high-tension metering enclosure, 15kV Vacuum Fault Interrupter padmount SWG, padmount
15kV-480 V liquid filled step-up transformers, aux power transformers, UPS, and control systems. - Tesla Megapacks (2XL) pre-purchase by Owner.
- All equipment installed outdoors on structural concrete pads with Code requirement fire protection systems.
- BESS Systems will be utilized for energy dispatch.
- Con Ed Utility Interconnection – 13.2 kV